Breaking News – Indiana Supreme Court clears hurdle for Rockport coal-to-gas plant

4


timthumb.php-2By Lesley Weidenbener

TheStatehouseFile.com

INDIANAPOLIS – The developers of a controversial coal-to-gas plant planned for Rockport say the Indiana Supreme Court has handed them a decisive victory in a battle over whether a deal to build it complied with state law.

But a utility company that’s been fighting the project argues the opposite.

The 5-0 ruling appears to eliminate a significant hurdle for Leucadia National, the plant’s developer, which had all but given up the project after legislative action made it likely it would need a new review.

The Supreme Court’s decision essentially makes that need for review moot, said Leucadia project manager Mark Lubbers.

“We won a complete and total victory,” Lubbers said. Still, company officials weren’t ready to talk Tuesday about when or if they’ll move forward with the plant.

Instead, Lubbers pointed to an April 30 statement in which the company said that even if it won in the courts, “only a clear reversal of position by the governor would enable the project to go forward.”

The statement came just after Gov. Mike Pence had said he would sign a bill into law that was meant to provide a new review of the project.

On Tuesday, a spokeswoman for Pence didn’t elaborate on the governor’s position on the plant or the decision. “We are reviewing the case, the contract and the relevant law,” said press secretary Kara Brooks.

The $2.8 billion Indiana Gasification project is the result of a sort of public-private partnership brokered by the company with the administration of former Gov. Mitch Daniels, for whom Lubbers had once been a top adviser.

The state wouldn’t take any ownership in the plant. Instead, under the deal signed by the Indiana Finance Authority, the state would purchase synthetic natural gas produced by the plant for 30 years at a fixed price and then resell it in the marketplace. The state would then pass the savings – or the losses – onto natural gas customers in the state.

Daniels argued that, over time, the cost of the synthetic fuel produced by the plant would be cheaper than natural gas. And meanwhile, the plant would use Indiana coal and provide jobs to Hoosiers.

But opponents – consumer groups and some utilities, including Evansville-based Vectren Energy – argued the state struck the deal before an explosion of shale gas extractions led the price of natural gas to plummet. The opponents say the deal is no longer a good one for Hoosiers.

Vectren Vice President Mike Roeder said the arrangement “is a loser in virtually all scenarios into the future. Given the fundamental changes that have occurred in the natural gas market since this project was proposed and the dated financial information in the contract, the project must be reviewed.”

At issue in the court case, though, was the wording of the state’s contract with Leucadia. The Indiana Utility Regulatory Commission approved the deal in 2011 but the Indiana Court of Appeals reversed that decision the following year, saying the contract included a clause that violated state law.

The Indiana Finance Authority and the Rockport developers agreed to drop that language from the contract, but that raised questions about whether the revised document would need another round of regulatory review.

Then earlier this year, the General Assembly passed a law that required such a review – but only if the Indiana Supreme Court had agreed with the lower court ruling or found the contract invalid.

That seemed so likely that Leucadia pulled the plug on the plant shortly after the legislation passed, despite having invested some $27 million in development. “We have been disappointed by the state’s breaking its commitment to the plant and the project,” Leucadia spokesman Mike Murphy said in April. “They have changed the rules in the middle of the game.”

But on Tuesday, the state’s highest court appeared to uphold the authority of the Indiana Finance Authority and Leucaida to resolve what it called a “definitional issue” in the contract. “Thus the issue is moot,” the court said.

That means the law requiring a second look at the contract won’t kick in, Lubbers said.

But Vectren officials disagreed, saying they believe the court decision means the Indiana Utility Regulatory Commission will need to review the contract, Roeder said.

The law passed earlier this year “now applies and, if the project is pursued by the developer, will govern consumer protection of any new contract.”

Even if that’s not true, Leucadia’s path to building the plant is not totally open. The Indiana Finance Authority still has one final sign off on the project. And it’s not clear how the Pence administration will approach that decision.

Also, Leucadia needs a loan guarantee from the U.S. Department of Energy to move forward.

The Indiana Supreme Court’s decision came just about three months after it heard oral arguments in the case. The review had been controversial because one of the state’s newest justices – Mark Massa – declined to recuse himself even though he had been Daniels’ general counsel when the Rockport deal was under consideration. Massa is also friends with Lubbers.

4 COMMENTS

  1. Did they ever get rid of the long term price guarantee? That’s the only way I could support it, and I still am not totally cracked up about it.

  2. This is great news for this region! This means the Vectren stranglehold on energy production will be challenged in some degree. Might be a great time to start a tier 3 business specializing in gas fixtures.

    • agree……….vectren is so against this i believe it has to be good for consumers……….good paying area coal jobs construction jobs……….also I believe no one can really believe natural gas prices will not rise in the next few years let alone 30yrs……….

Comments are closed.